🛠️ Data Consolidation & Facility Acquisitions Project
📍 Client: Duke University
👤 Role: Implementation Project Manager
📅 Timeline: April 1 – May 1
💰 Budget: $47,000
👥 Team Size: 6
🧭 Methodology: Hybrid
🎯 Objective
Execute a fast-tracked data consolidation and facility acquisition project in 4 weeks (original timeline: 9 months), including integration of legacy data and implementation of a new credentialing system.
⚠️ Challenges
Delayed access to legacy data; access was only granted on the project start date (4/1)
Data received in incorrect format, causing further delays
Client team required onboarding, data validation, and mapping support during the active project window
🔧 Actions Taken
Facilitated weekly status calls to align on data mapping, code conversions, and validation
Coordinated cross-functional collaboration between data SMEs, system trainers, and implementation leads
Identified and addressed training and knowledge gaps in real time through working sessions
Implemented issue tracking and timeline adjustments to accommodate for initial data delays
✅ Results
Successfully implemented project on time, despite compressed schedule and data issues
Achieved strong user adoption through targeted optimization sessions post-implementation
Project delivered within budget and met all core deliverables in a fraction of the original timeline